There must be:

A:  a circuit breaker with high sensitivity, adequately sized;

B: a point of connection to the power mains;

C: a point of connection to the water mains (only for water-cooled appliances in case of connection to the water mains); to comply with the pressures available on the water networks, if necessary, install a special pres- sure reducer on the fixed system, upstream of the appliance. The device indicated must be installed in accordance with the regula- tions in force in the countries of destination and considering the requirements of the EN 60335-1:2012 standard and respective amendments (including A14:2019). For EU member countries: Denmark, Norway, Sweden, Finland, the device must withstand an upstream pressure of at least 1.0 Mpa (10 bar). In case of clarifications, indications on the choice of the reducer and any other requirement, contact technical support;

D: a point of discharge (optional) 

The machines must be positioned on the ground only, on floors:

  • that are not sensitive to heat or flammables;
  • perfectly levelled;
  • with a regular surface and free of roughness;
  • that can support the device at full load.


Keep the illustrated minimum clearances around the device: this will facilitate connections to utilities and maintenance.

 

The devices require ventilation at the back, where the vents and coolant unit are found. Therefore, do not place them against the wall but keep them approximately 5 cm away. In order to prevent accidental movements from excessively approach the device to the wall, install the provided spacers on the back of the device (especially if the device is assembled on wheels).